Marimaca Copper unveils US$450 million Sprott financing deal
Marimaca Copper Corp. [MARI-TSX] said it has secured investment committee approval from Sprott Resource Lending Corp. and its affiliates for a US$450 million financing package to support development of the Marimaca Oxide Deposit (MOD) in Antofagasta, Chile. The company continues to advance the project toward a final investment decision with critical path items remaining on schedule through 2026 and 2027.
A 2025 feasibility study outlined the potential for MOD to be a low capital intensity, high margin mine with proven and probable reserves of 748,000 tonnes of contained copper, supporting a mine life of 13 years. Pre-production capital expenditures are pegged at US$587 million.
Marimaca said it has executed a term sheet for an up to US$425 million project finance facility and up to US$25 million equity investment from Sprott. It said the project finance facility and equity investment remain subject to the completion of legal and financial due diligence by Sprott, the negotiation and delivery of definitive documentation and the satisfaction or waiver of customary conditions precedent to financial close and each applicable drawdown.
The project finance facility consists of a US$425 million senior secured facility with a term of 7.5 years. Upon receipt of the final investment decision and subject to customary conditions, including execution of definitive documentation, US$100 million will be released to Marimaca. Subsequent advances are available to the company upon satisfaction of customary conditions precedent.
Interest accrues at the floating rate equal to 5.75% per annum plus the greater of the secured overnight financing rate and 2.75% per annum. Interest is paid quarterly, and 85% of interest costs may be capitalized until the end of the availability period.
Principal repayments will commence on March 21, 2031, and Marimaca shall repay the principal amounts of the project finance facility inclusive of any capitalized interest and other costs, in an amount equal to 4.0% of the outstanding principal amount of the project finance facility on a quarterly basis. The remainder of the principal payments are due upon maturity.
The project finance facility allows the company to continue to advance the Pampa Medina project at its desired pace alongside construction of the MOD. Pampa Medina is located approximately 26 kilometres north of MOD. “The emerging scale and quality of Pampa Medina presents a potentially transformational growth opportunity for Marimaca, and we are excited to have a partner that recognizes the significant potential of both assets and shares our ambition to build a leading Chilean copper company,’’ the company said in a press release.
On November 23, 2026, Marimaca shares closed at $5.97. The shares currently trade in a 52-week range of $13.40 and $5.53.
Proceeds of the project finance facility are to be used for the MOD project’s construction and ramp-up costs, working capita requirements, financing costs and general corporate purposes. Following investment committee approval, Marimaca Copper will progress definitive documentation, complete the broader construction financing package and work to satisfy the conditions required for final investment decision and financial close.