Silver Tiger Metals Inc. [TSX: SLVR; OTCQX: SLVTF; FSE: 10C] provided a construction update for the El Tigre Project located in Sonora, Mexico. Construction is on schedule for commissioning and first pour in December, 2027.
Buildout of Mexican engineering and construction team is nearing completion with a total of 166 persons on site and 100,000 man-hours logged since start of construction.
Detailed engineering by Kappes, Cassiday & Associates (KCA) and Kappes, Cassiday del Norte S de RL de CV (KCN) pursuant to the engineering procurement and construction management (EPCM) contract for the project is proceeding on schedule.
Procurement on long-lead items is complete, including crusher plant, conveyer and stacking system, and the Merrill-Crowe plant and refinery.
Land clearing and flora/fauna management for the total construction area is 60 per cent complete. Installation of construction offices has been completed.
Engineering for improvements to the 46-km road built from Colonia Morelos to El Tigre is complete. The contract to improve this road has been awarded and work has begun, with 25% of road improvements complete.
The major earthworks contract has been awarded for the heap-leach, ponds and crusher platforms and these earthworks have begun.
Comision Federal de Electricidad (CFE) has granted access to grid electrical power for the El Tigre project.
Glenn Jessome, president and CEO, stated: “Our on-site engineering and construction team is nearing 200 persons. Earthworks have begun and land clearing is over 60% complete. Long-lead items such as crusher, conveyor, stacking and Merrill-Crowe have been ordered. We are very pleased that mine construction is on schedule for commissioning and first pour in December, 2027.”
The company has transitioned to exploration drilling targeting the high-potential vein systems north of the main El Tigre area. This priority zone aligns directly with the El Tigre North mine design outlined in Section 24 of the company’s recently filed preliminary economic assessment (PEA) dated January 22, 2026. The PEA also highlighted significant exploration upside beyond the defined underground and Stockwork resources, including the prospective areas 700 metres to the north.
Silver Tiger is constructing the El Tigre stockwork zone project, a silver and gold heap-leach project located in Sonora, Mexico. The project is 100% owned by Silver Tiger and covers over 37,000 hectares.
Silver Tiger has entered into an EPCM contract with Kappes, Cassidy & Associates (KCA) and Kappes, Cassiday del Norte (KCN) to assist in the construction of the mine and process plant at El Tigre. The company has also now hired its own experienced mine construction executive team to work with KCA and KCN.
Commissioning and first pour are targeted for December 2027. The board of directors of the company have approved the construction decision for El Tigre.
Resource World Magazine Inc. has prepared this editorial for general information purposes only and should not be considered a solicitation to buy or sell securities in the companies discussed herein. The information provided has been derived from sources believed to be reliable but cannot be guaranteed. This editorial does not take into account the readers investment criteria, investment expertise, financial condition, or financial goals of individual recipients and other concerns such as jurisdictional and/or legal restrictions that may exist for certain persons. Recipients should rely on their own due diligence and seek their own professional advice before investing.