GoGold Resources updates Los Ricos South Project construction, Mexico

Share this article

GoGold Resources Inc. [TSX: GGD; OTCQX: GLGDF] provided an update on construction at its Los Ricos South Project in Jalisco, Mexico. The project is progressing on schedule, and the company reiterates first silver pour in the second quarter of 2028.

“Construction at Los Ricos South continues to progress according to plan with site clearing and earthworks about halfway complete,” said Brad Langille, president and CEO. “Reflecting on recent volatility in the precious metals, it is good to note that our project is a very high-margin project, which is less impacted by a decrease in metal price than most. Our very strong balance sheet and substantial cash flows generated at our operating mine in Parral further derisks the project and we do not foresee any need for future equity or debt offerings to complete the project. Based on internal estimates using $45/oz silver, we see our cash reserves maintaining a minimum of US$100 million over the course of the build.”

Los Ricos South construction highlights: Active site works – site clearing and earthworks at the process plant site are approximately 48% complete with 180 contractor personnel on site. All long-lead orders placed – all long-lead equipment orders have been placed, with procurement continuing on schedule. The long-lead orders include the SAG mill, tailings filter, crusher, electrical switchgear, Merrill-Crowe plant, conveyors, slurry pumps, hydrocyclones, feeders and screens, and paste plant pumps.

Plant design – the design by M3 and DENM Engineering is 95 per cent complete. Vendor design specifications being inputted to the finals design.

Paste plant design – the design is being carried out by RMS of Sudbury, Canada. The current progress will allow the start of construction in January, 2027.

Underground mining contractor selected – Cominvi planned to mobilize to site in Q4 2026. Portal designs have been completed by WSP and associated earthworks have begun.

Schedule maintained – construction and procurement remain on or ahead of plan, with first silver pour reiterated for Q2 2028.

To date, the company has spent US$21 million on the project, with US$52 million committed to date.

Key schedule milestones: Los Ricos South key schedule milestones

Earthworks commenced August, 2026; underground mine plan optimization commenced August, 2026; start of powerline installation — Q1 2027; concrete foundation pouring January, 2027; portal development/ramp blasting January, 2027; paste plant construction begins January, 2027; hill-slope stabilization/mining Main/Abra zone March, 2027; SAG mill delivery to site May, 2027 and plant commissioning begins January, 2028.

Halifax-based GoGold Resources is focused on operating, developing, exploring and acquiring high-quality projects in Mexico. The company operates the Parral tailings mine in the state of Chihuahua and has the Los Ricos South Project, which is in development with a construction decision approved by the board, and Los Ricos North exploration and development project, both in the state of Jalisco.